on 2024 Dec 17 9:16 AM
Hi all,
Against a single PR 4 no of PO's were created and all are deleted except one PO. PO value is less than that of PR & WBS also having Budget. But system throwing error budget exceed which is of 4 times that of PR value. Pl suggest a suitable solution to resolve the issue.
Request clarification before answering.
Run transaction CJBN to rebuild budget availability. You can also run CJEN to rebuild the PS Info structure. It's a good idea to schedule these transactions to run periodically.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.