Mismatch in CJI5/Table Commitment Values & PR value

pachowdary
Explorer
0 Kudos
163

Hi all,

Against a single PR 4 no of PO's were created and all are deleted except one PO. PO value is less than that of PR & WBS also having Budget. But system throwing error budget exceed which is of 4 times that of PR value. Pl suggest a suitable solution to resolve the issue. 

Accepted Solutions (0)

Answers (1)

Answers (1)

Ken_Melching
Product and Topic Expert
Product and Topic Expert
0 Kudos

Run transaction CJBN to rebuild budget availability.  You can also run CJEN to rebuild the PS Info structure.  It's a good idea to schedule these transactions to run periodically.