4 weeks ago
Hi Team,
We are not able to change the Migration Key date to from 12/31/DIGITS to 31/03/DIGITS, could you please do form your end
app name: Define Settings for Legacy Data Transfer
Request clarification before answering.
This issue is happening because the status for the migration key date must be set back to “ongoing” as the screenshot as I could see.
To Change the date, the status for the migration key date must be set back to “In Preparation” to change the date. Afterwards, for running the migration the status must be switched to “ongoing”.
Please refer to the KBA ##2754615 - SAP S/4HANA Migration Cockpit: Information about Posting Date / Migration Key Date for your reference.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
93 | |
15 | |
9 | |
8 | |
5 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.