on 2009 Jan 28 2:13 PM
Hello SAP Guru
I have run M-T-O 20 strategy.I create material master,bom,work center,routing & sales order
BUT
**when i have run MRP in MD50 only get messege MRP CARRIED OUT FOR FERT MATERIAL
MESSEGE NO. 61054
& have disply one planned order ie
not develop semifinish,raw material(md04)only finished material
i also see mrp list in MD05 but there is no any list display only get message 61088
Request clarification before answering.
Hi,
I think you want to tell is MRP not carried out for Dependent Requirements, Correct?
Then problem may be,
- Check in MRP 4 view of BOM components for requirement types.If you want Planning Proposal with account assginment type of sales order then set requriement type as Individual or Individual and collective both.
- If it is maintain as Individual and still problem is there then check validity date of BOM and Production version also.
- Same thing applicable (Point 2) for valid From to To lot size of BOM and Production version also.
- Check Planned order of Fert which was generated during MRP , BOM is exploded or not?
Regards,
Dhaval
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
sir i try this type procedure for your response but it was same ERROR "MRP CARRIED OUT "
MESSAGE NO 61054
My procedure is for subconracting:
i create subcontracting material then it's BOM ONLY i have not maintain ROUTING
Because my subcontacting procedure is MATERIAL WISE not operation wise.
How shold solve this problem?
pls in detail scenario.
yogesh patil
SAP PP
User | Count |
---|---|
100 | |
8 | |
7 | |
5 | |
5 | |
4 | |
4 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.