on 2025 Feb 17 7:45 PM
We have maintenance plans set up to generate a PM based on a counter reading.
MP1 - Weekly hour meter reading for counter 1 is entered.
MP2 - PM generated for equipment every 800 hours based on counter 1.
At 800 hours MP2 generates a PM for the technician to service the equipment. However, based on equipment availability and scheduling the equipment has 850 hours when the service is completed.
Is it possible to add a measurement reading to MP2 for hour meter reading once service is completed so that MP2 next service would be at 1650 hours instead of 1600?
Request clarification before answering.
Greetings,
you need to maintain shift factors on maintenance scheduling parameters tab. Maintain both at 100%.
Best regards, M.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
91 | |
11 | |
9 | |
8 | |
6 | |
4 | |
4 | |
4 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.