on 2008 Feb 06 7:33 PM
Hi all,
some cost estimates are marked and are in status 'Vo'. These materials when released for current period thr CK24 shows error 'Period closing has not taken place yet' . But when released for previous period gived error ' Release to Late' .?
How can these materials be released ?
points will be rewarded for helpful answers
Is your client also using Material Ledger or Transfer Prices? If this is the case, the standard costs from the cost estimate have to be in synch with the preliminary valuation for actual costing. Period closing would be the generation of closing entries in the material ledger.v
If this is not the case, then check whether the MM tables (accounting view of the material master are on the period for which you are trying to release).
Edited by: Janet Dorothy Salmon on Feb 7, 2008 9:38 AM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
109 | |
8 | |
6 | |
6 | |
6 | |
6 | |
5 | |
5 | |
4 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.