on 2008 Apr 04 10:59 AM
I am creating a scheduling agrmt. [me31l]
in the item overview I get message
material not maintained by purchasing
looking into mat mstr., the puchasing grp. is maintained.(purchasing tab).
where do I undo this error message.
Request clarification before answering.
according to the erro it means theourchasing view is not maintianed for the plant u are creating the agrrement
please go to the tcode mm50 and use the key for the purchasing and try to ensure that purchaisng data is maintined there
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
purchasing val key field = empty , for both ref. materail and this new mat.
if I create me31L for the ref mat., I get (DE) language text issue only, I can get around this with writing some text for DE(additional data).
but if I go for the new material (referenced from the original mat), I get the error msg.
sos I am not sure about the purchasing key , since it is empty in both cases.