material master before actual costing

Former Member
0 Likes
688

before I run CKMSTART for my company code/plant, I upload material master, in accounting view1, I should leave 2 or 3 for price determination field (i try to use actual costing), if I upload 3, after I run CKMSTART, does it change to 2?

I should upload material master, do the stock balance upload then run CKMSTART or vice versa? 

in CKMSTART, I'm not sure which exchange rate type I should use, but other people already run CKMSTART for other plants, how can I find the previous ML exchange rate type for other plants?

do we have CKMSTOP if  I want to clean up material for one company code/plant but leave other plants keep using material ledger?

Accepted Solutions (0)

Answers (1)

Answers (1)

former_member182575
Contributor

CKM9 for configuration settings.

Regards

Waza

shailendra_CA
Discoverer
0 Likes
Create master data and load inventory after CKMSTART. This worked for me till now.