material master and info record calender

jerrysam
Participant
0 Likes
669

Hello ,

Lead-Times in Material Master are based on 5 working days. Lead-Times in Info-Records are based on 7 calendar days.

can we maintain both on same level

 

any suggestions..?

Accepted Solutions (0)

Answers (1)

Answers (1)

Prasoon
Active Contributor
0 Likes

Hi,

In material master, the PDT is set at plant level and the plant has factory calendar.

I would suggest you to set the PDT in info-record with plant combination (ME11 or ME12 with plant) and test the behavior again.

Regards,

jerrysam
Participant
0 Likes
Hello Prasoon, May I know before changing the calenders which process or funcationalities will affected by changes...?