on 2024 Mar 12 8:44 AM
Hello ,
Lead-Times in Material Master are based on 5 working days. Lead-Times in Info-Records are based on 7 calendar days.
can we maintain both on same level
any suggestions..?
Request clarification before answering.
Hi,
In material master, the PDT is set at plant level and the plant has factory calendar.
I would suggest you to set the PDT in info-record with plant combination (ME11 or ME12 with plant) and test the behavior again.
Regards,