Material loss

Former Member
0 Kudos

Hi

I have a stock of 10 tonnes cement, because of moisture at the time of issue i could issue only 9 tonnes

after issuing 9 tonns (entire material) , system shows 1 tonn exists in stock, but physically there is no stock (loss becoz of moisture)

how to adjust this 1 tonn value in SAP?

Thanks

Raju

Accepted Solutions (1)

Accepted Solutions (1)

BijayBarik
Active Contributor
0 Kudos

Hi,

For you materail loss due to moisture, you can follow to enter/ post the goods which are loss due to moisture

Option-1:Scrap it

Scrap it with 551movemnt type as 1 tonn value

Option-2:Go for physical Inventory

Do a physical count and post the difference.

Regards,

Biju K

Answers (4)

Answers (4)

Former Member
0 Kudos

Hi,

I advise you not to do any scrapping. Becasue in this case there won't be any scrap materials available. Please perform physical verification for inventory.

Try this.

Step 1A

MI31

Step 1B

MIO1

Step 2 - MI21

Step3A - MI04 Step3B - MI05

Step 4- MI20

Step 5 MI07

Hope it will work.

Thanks

Prasada

Former Member
0 Kudos

Hi

I would advise you following options:

1.Do the stock adjustment for 1Tonne of stock - This can be done by normal physical inventory process of counting and posting the differences siting reason as Moisture loss.

2.Scrapping - Scrapping quantity of 1 Tonne using 551 movement

3.Deivery Receipt reversal using 512.

However,before going ahead I would advise you to check the account postig which must be acceptable to Finance and accounting. I would advise physical inventory method from account perspective.

Cheers

Rahul

Awards plz if it helps you.

Former Member
0 Kudos

Hi,

Remove 1 tonne material by Movement Type 512 (Receipt of delivery without charge - reversal).

Regards.

Pravin

Edited by: Pravin Matkar on Sep 18, 2009 12:15 PM

Former Member
0 Kudos

Hi,

U can dump or scrap the damamge material by movement type 551 in SAP.

transfer the material to damage storage location if have one and from there issue the material to cost center for dump by movement type 551.

Regards,

AM