material availability date is before sales order creation date

Jayd_T
Newcomer
0 Kudos
209

Hello,

We are experiencing issues with a few sales orders where the material availability date is being determined before the order creation date.

We have checked the scheduling settings for the sales document type in SPRO, and backward scheduling is not enabled.

What could be the possible reason for this?

Thank you in advance for your response.

Accepted Solutions (0)

Answers (1)

Answers (1)

Dominik_Tylczynski
SAP Champion
SAP Champion
0 Kudos

Hello @Jayd_T 

See the following notes:

3551399 - ATP Confirmation Date in the Past for Sales Orders

The issue arises when there are no 'X' in the field DlvSchdlg and TranspSchd flag in transaction OVLY for order type.

 

2221849 - Customizing and process flow of SD scheduling

Material Availability date
In case of backwards scheduling: material availability date = loading date – pick pack time
In case of forwards scheduling: material availability date = loading date – pick pack time or current date

 

If all else fails, debug according to the note 2220102 - Debugging guide for SD scheduling

Best regards

Dominik Tylczynski