Dear all
I´m wondering why SAP B1 allows to exceed a master agreement (sales) which is limited to a specific quantity.
For example: Master agreement of 1000 pcs -> SAB B1 allows to add purchase orders with way more than 1000 pcs.
I´m looking for a system warning when 1000 pieces are achieved.
I`ve been already checking the document settings for master agreements, but with no solution so far.
Can anyone help?
Thank you very much
Request clarification before answering.
Hi balzerni,
It appears that this option is available/meant for Purchasing documents only.
The option is When Quantity/Amount Exceeds Planned Quantity/Amount for Documents under Administration → System Initialization → Document Settings → General tab.
Kind regards,
ANKIT CHAUHAN
SAP Business One Support
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
87 | |
12 | |
10 | |
5 | |
4 | |
3 | |
3 | |
3 | |
2 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.