on 2016 Apr 29 12:21 AM
Dear Seniors,
We have a bunch of Planned Orders created which have only Basic Dates and no Scheduled Dates.
The routings used at that time were dummy.
Please let me know if there is a way to schedule a bunch of Planned Orders in mass, backwards so that the Basic End Date is not changed, and the Basic Start can follow the scheduled date.
I have tried by using the MRP but it does not work for Firmed Planned Orders.
If I un firm them, then the dates will be totally changed. We want to keep the Basic End Date unchanged.
Thank you,
Alex