cancel
Showing results for 
Search instead for 
Did you mean: 

Mass schedule Planned Orders ?

Former Member
0 Kudos
301

Dear Seniors,

We have a bunch of Planned Orders created which have only Basic Dates and no Scheduled Dates.

The routings used at that time were dummy.

Please let me know if there is a way to schedule a bunch of Planned Orders in mass, backwards so that the Basic End Date is not changed, and the Basic Start can follow the scheduled date.

I have tried by using the MRP but it does not work for Firmed Planned Orders.

If I un firm them, then the dates will be totally changed. We want to keep the Basic End Date unchanged.

Thank you,

Alex

Accepted Solutions (1)

Accepted Solutions (1)

rupesh_brahmankar
Active Contributor

Hello,

Please refer my reply from this discussion.

Best Regards,

R.Brahmankar

Former Member
0 Kudos

Thanks a lot Brahmankar for your helpful input !

Answers (0)