on ‎2012 Feb 06 3:16 AM
Hi,
We have migrated from Discrete to repetitive.
But there were some dependent requirements and Production orders open.
Every time i run mrp i get planned orders for these requirements.
I have checked the demand in MD62 but i could not find any demand in those dates.
How to delete these requirements in mass or at table level.
I have been through some links and found that it can be deleted at table level using MDPB table if yes can you tell me how to use it.
Thanx in advance.
Sandeep
Request clarification before answering.
Try running MRP by setting up a background job during off-peak hours with the following parameters...
Processing key NEUPL Regenerative planning
Create purchase req. 2 Purchase requisitions in opening period
Schedule lines 3 Schedule lines
Create MRP list 1 MRP list
Planning mode 3 Delete and recreate planning data
Scheduling 2 Lead time scheduling and capacity planni
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello,
Use Tcodes- MD74 & MD75 to delete OLD PIR's in system which are not assigned to any sales requirement.
So run MD74 & MD75 then close/delete any open production order before running new MRP.
Regards,
Anup
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanx for all the inputs.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
| User | Count |
|---|---|
| 36 | |
| 27 | |
| 21 | |
| 4 | |
| 4 | |
| 4 | |
| 4 | |
| 3 | |
| 3 | |
| 2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.