on 2022 Sep 08 9:03 PM
Hello Experts,
I searched the other blogs, but could not find a solution for -> I need to update work center in Routing via CA02 for a material. But if I want to do so for 500-600 materials what and how can I do it, CEWB got through it, but it accepts Group number, not material number for any of the selection criteria.
Any suggestion if Group number id correct way to proceed with or advise,
Thanks in advance,
Request clarification before answering.
Hi John, you can do this in CEWB.
Current Working Area = SAP_Operation
Click the 'Additional Selection Criteria' button
Input materials / plant / work centre and execute.
Select relevant tab - ie if you are changing operation times select 'Processing Times' tab. Select all operations, highlight relevant column and goto Extras --> Mass Change
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
98 | |
8 | |
7 | |
5 | |
5 | |
4 | |
4 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.