Make to Order

Former Member
0 Kudos
243

Hi friends,

We are using strategy 20 i.e., make to order scenarios where after received of sales order all it component get reserved and dedicted to that respectively sales order.

Now the issue raise when the 5 to 6 sales order are been created where all this sales order has common semi finished. But after MRP run system create different planned order for each sales order. We want that system should club the respectively semi-finished planned order.

Please comment.

Regards,

Sun

View Entire Topic
rupesh_brahmankar
Active Contributor
0 Kudos

Hello,

To club the respectively semi-finished planned order define individual. collective indicator as 2 only collective requirement for your  semi-finished in MRP 4 view.

Also use the period lot size like WB, MB to club the requirement run the MRP  and check the results.

Best Regards,

R.Brahmankar