on 2015 Oct 14 5:48 AM
Hi friends,
We are using strategy 20 i.e., make to order scenarios where after received of sales order all it component get reserved and dedicted to that respectively sales order.
Now the issue raise when the 5 to 6 sales order are been created where all this sales order has common semi finished. But after MRP run system create different planned order for each sales order. We want that system should club the respectively semi-finished planned order.
Please comment.
Regards,
Sun
Request clarification before answering.
Hello,
To club the respectively semi-finished planned order define individual. collective indicator as 2 only collective requirement for your semi-finished in MRP 4 view.
Also use the period lot size like WB, MB to club the requirement run the MRP and check the results.
Best Regards,
R.Brahmankar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
100 | |
13 | |
11 | |
5 | |
5 | |
5 | |
3 | |
2 | |
2 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.