on 2015 Oct 14 5:48 AM
Hi friends,
We are using strategy 20 i.e., make to order scenarios where after received of sales order all it component get reserved and dedicted to that respectively sales order.
Now the issue raise when the 5 to 6 sales order are been created where all this sales order has common semi finished. But after MRP run system create different planned order for each sales order. We want that system should club the respectively semi-finished planned order.
Please comment.
Regards,
Sun
Request clarification before answering.
Dear Sun,
1. Individual/collective indicator "2" collective requirements for the Header Material so that you will get your dependent requirements clubbed together. This has to be done to material master of the semi-finished material in MRP 4 view.
2. Also with reference to the Availability check in MRP3, please check the Checking group settings in SPRO.
This would solve this issue.
Regards,
Vibin.V.J
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello Sun ,
Make to order, Planning strategy: 20 ,
You already mention on your earlier post, Semi finished material common for all the sales order.
So when you select the Individual/coll.-1 that means the stock is link to specific that sale order and create the planned order with respect to the sales order individual,
If you select 2-collective requirement that means the stock is free and you can use it for any order, Qty are clubbed for all the orders. Here it is not reserved for specific order but with respect to sales order system create the req of all qty.
I hope this information help to you
Thanks & regards
Umesh Mali
.
User | Count |
---|---|
91 | |
11 | |
9 | |
6 | |
6 | |
4 | |
4 | |
4 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.