Maintenance Plan with Completion Indicator CHECKED generates WOs even without previous WOs completed

0 Likes
385

Hi All.

Has anyone faced a similar issue? We have 31 exactly same maintenance plans. They are scheduled and have already generated some calls. All of a sudden, plan number 27 and 28 have started work orders without the previous orders being completed. The following are the details of the MPs:

- Cycle/Unit = 5 days

- Offset = 0 day

- Shift Factor for Late Completion = 100%, Tolerance (+) = 0%

- Shift Factor for Early Completion = 100%, Tolerance (-) = 0%

- Cycle Modification Factor = 1.00

- Call Horizon = 5 days

- Scheduling Period = 365 days

- Completion Requirement = CHECKED

- Scheduling Indicator = Time

Accepted Solutions (0)

Answers (1)

Answers (1)

Ritesh_PR
Explorer
0 Likes

Hi @indraniljoshi1989,

Notice that you've activated enhancing call horizon functionality (switch -  EAM_SFWS_MPLAN_OPEN_HORIZ_DAYS) which allows you to set call horizon in days. This may be the cause for some plans bypassing the completion requirement check. 

Check this SAP note and implement the corrections - 1849123 - EAMCC: Enhancing the call horizon- check for call completion - SAP for Me

Regards,
Ritesh PR