Hi,
May I ask for help in explaining why the Call Date for the first Call Object line was called when there is a Call Horizon of 45 DAYS? The details of the Maintenance Plan are as follows:
Maintenance Plan created and scheduled : 29.01.2024
Cycle Unit : 1000 HR
Call Horizon : 45 DAYS
Start Counter Reading : 75830 (counter reading when Maintenance Plan was created)
First Planned Date : 28.05.2024
First Call Date : 17.03.2024
Scheduling indicator : 3 - Performance Based
What is the basis of the Call Date? Shouldn't it be based on the Call Horizon? Thank you
Request clarification before answering.
Greetings,
as per documentation:
So according to your maintenance plan a call object should be created 45 days before the cycle 1000 hours is reached. The estimated date when cycle is reached is calculated based on counter annual estimate and regular measurement documents input.
You can also try clicking on the call algorithm button in IP10. System should show how it calculated call number data.
Best regards, Matjaž.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
| User | Count |
|---|---|
| 33 | |
| 17 | |
| 14 | |
| 13 | |
| 9 | |
| 4 | |
| 2 | |
| 1 | |
| 1 | |
| 1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.