Maintenance Plan Call Dates called earlier than Call Horizon

lmoc
Explorer
0 Likes
1,736

Hi,

May I ask for help in explaining why the Call Date for the first Call Object line was called when there is a Call Horizon of 45 DAYS? The details of the Maintenance Plan are as follows:

Maintenance Plan created and scheduled : 29.01.2024

Cycle Unit : 1000 HR

Call Horizon : 45 DAYS

Start Counter Reading : 75830 (counter reading when Maintenance Plan was created)

First Planned Date : 28.05.2024

First Call Date : 17.03.2024

Scheduling indicator : 3 - Performance Based

 

What is the basis of the Call Date? Shouldn't it be based on the Call Horizon? Thank you

Accepted Solutions (1)

Accepted Solutions (1)

memem
Active Contributor
0 Likes

Greetings,

as per documentation:

matjazmoser_0-1719477101051.png

So according to your maintenance plan a call object should be created 45 days before the cycle 1000 hours is reached. The estimated date when cycle is reached is calculated based on counter annual estimate and regular measurement documents input.

You can also try clicking on the call algorithm button in IP10. System should show how it calculated call number data.

matjazmoser_1-1719477339956.png

Best regards, Matjaž.

lmoc
Explorer
0 Likes
Thank you Matjaz. I have checked the algorithm button and I have the data below
lmoc
Explorer
0 Likes
Annual Estimate = 2367.52 Activity per day = 6.49 Start Counter Reading = 75830 Next Counter Reading = 76830 The first object was called at 17.03.2024 which is not 45 days from the Planned Date of 28.05.2024. My question is why was the Maintenance Order called at 17.03.2024? Thank you.
memem
Active Contributor
0 Likes
@lmoc Can you post a screenshot of IP10 transaction for your maintenance plan. Can you also post a screenshot of measuring documnets for your counter?
lmoc
Explorer
@memem I have attached the screenshots of IP10 and the Measuring Documents in the original question. May I ask if you may check if you can see it? Thank you
memem
Active Contributor
0 Likes
Greetings, how often do you schedule the maintenance plan - do you run IP30 daily? It is possible that the cycle is reached before 45 days. Perhaps also think why do you use call horizon - would it be okay if the maintenance call object would be created when the cycle reaches 1000?
lmoc
Explorer
0 Likes
Yes, IP30 is run daily via background job. We are using call horizon for MRP consideration. Thank you.
lmoc
Explorer
UPDATE: After reading several articles, it seems the Call Dates were called earlier because of the 30 DAYS entered as parameter in IP30. Since the Call Dates fell to the Interval entered in IP30, the call objects were created. Kindly confirm if this analysis is correct. Thank you.
memem
Active Contributor
Greetings, well that certainly sounds about right!
lmoc
Explorer
0 Likes
Thank you! You're time is greatly appreciated