Maintenance call dates

preethialevarthi
Participant
0 Kudos
152

Hi Team,

We have a Maintenance Plan of the cycle of 1 Year, start of cycle - 01/05/2022 and Call Horizon is 30 Days. There are no shift factors or Tolerance set up. For this year why the work order got created automatically on 29/03/2024 instead of 01/04/2024.

Regards,

Preethi

VijayGS
Explorer
0 Kudos

Please see the reply.

Accepted Solutions (0)

Answers (1)

Answers (1)

VijayGS
Explorer
0 Kudos

Hi Preethi,

Could you check the calculation log for the generated call object?

You will find this particular call in the plan, where you can choose the specific call and see the calculation details. Here you will find the date calculation details.

I am not sure, but also check if there is an impact of the leap year.

Regards,