on ‎2023 Dec 27 5:55 PM
Hi All,
I need to lock multiple position ID at one go & also need to lock budget for multiple projects /wbs element at one go .
Can anyone please suggest by which t-code I can do these ?
Thanking you .
Mehbub
Request clarification before answering.
Hi Mohammed,
For IM program positions you have a system status BMLK, unfortunately not aware of any option for a mass processing at the level of IM program positions.
When it comes to WBS you have a transaction CNMASSSTATUS, but you will need to configure a User Status that blocks budget changes.
Regards,
Paulo
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Many thanks Paulo .
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
| User | Count |
|---|---|
| 39 | |
| 22 | |
| 21 | |
| 5 | |
| 4 | |
| 4 | |
| 4 | |
| 3 | |
| 2 | |
| 2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.