on 2024 Oct 11 12:50 PM
I am not able to identify a link between a PO and the material document posted from ZME2O.
Is there any field or flag that allows me to know if the subcontract PO has been issued?
Thanks!
Request clarification before answering.
Hello @daria_garrido
I don't think that a material movement providing a subcontractor with components is linked directly to subcontracting purchase orders. ME2O (I assume your ZME2O works the same) calculates net requirements of components to be provided and moves them to the subcontractor in bulk. Therefore several subcontracting POs can be supplied with a single material movement.
Best regards
Dominik Tylczynski
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
98 | |
39 | |
8 | |
6 | |
5 | |
3 | |
3 | |
2 | |
2 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.