Hello Experts,
There is a requirement from the client in the ECC system for REM, that system to create only 1100 pcs/day per production line for multiple header materials (i.e. not specific to any single material). The total planned orders generated for a particular production line should not be more than 1100 pcs/day, this includes all the materials that will use that production line. Any more requirements should go to next day's planned order.
Required master data is maintained with the production version for the materials.
Looking forward to any kind of suggestions which will solve this.
Best Regards,
Onkar Mundhe
Request clarification before answering.
You can use Quota arrangement with maximum quota to a Production version in a week or day.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
98 | |
16 | |
6 | |
5 | |
5 | |
4 | |
4 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.