Limit of number of operations in SAP PM work orders.

elvin_enc
Explorer
0 Kudos
1,044

I make an PM order with more than 10 operations, but after save it, i only can see 10 operations inside de order. If i run IW49 TC then i can see the complete order list, apparently my pm orders configuration has a 10 operation rows limitation.

by SPRO, How can I limit or unlimit the number of operations inside a PM order??

View Entire Topic
Former Member
0 Kudos

you can design a view profile and assign 033 as screen area in it. 033 screen area for operation has 15 lines of operations. However in screen you can only 15 operations...to check further operations you have to scroll down the operation list.

Former Member
0 Kudos

Hi Prakhar

Can yu please tell me how do we this with the one you have suggested in SAP

Former Member
0 Kudos

Hi,

   Under IMG node Plant maintenance--->Maintenance and service processing---->functions and setting for order types---->basic order view---->define view profile design a profile which contains hedaer data and operation data. screen shot below. Then assign this view profile to respective order type planning plant combination in the immediate below node. When you create an order then for respective plant order type combination operation tab will be shown with 15 lines.