on 2020 Aug 05 11:21 AM
Hi All,
In out solution we use phantom materials, for Finished Product and that phantom materials have their own BOM.
Issue is that in the report KKBC_ORD we are seeing Target quantity and target cost for these phantom materials instead real materials.
Who knows is it standard behavior of this report or we something miss in configuration?
Thanks in advance for any ideas!