on 02-22-2008 9:45 AM
Hi,
When I am assigning configurable material in service order as components I am getting as error "no configurable material can be assigned to the order'
If anyone byepasssed the error please let me share.
Regarsd
Sendil
Hi Sendil,
Service and maintenance orders can't handle configurable components. Technically, the service and maintenance order is derived from a PP order. Within a PP-order, configurable components are allowed and they are used to create suborders. An example for that scenario is an order to produce a configurable car: A customer ordered a red car with four wheel drive. So an order is created for a car with (at least) two configurable components: a configurable bodywork (characteristic is "Red") and a configurable drive (characteristic is "four wheels"). After entering these components, two suborders are to be created because the bodywork and the drive have to be produced, too.
This is standard, and unfortunately it will not be changed within the
next releases. Message was introduced with note 72404.
Regards
Amber