on 2014 Nov 18 6:38 AM
Dear All
Currently for one of the product we have some storage limitations due to constrain in Storage space in Warehouse
Sceanrio
Following are delivery requirements:
(1) Delivery required from vendor need to split into 2 to 3 deliveries per week to control monthly inventory and storage space
Example
MRP ran propose X qty in a PR for wk 46
Hence the deliveries for wk 46 should be as follows:
Mon -> deliver X1 qty
Wed -> deliver X2 qty
Fri -> deliver X3 qty
Total X qty
2) Also deliver quantity should be fixed sizes, Ex the total quantity proposed by MRP X= 1080 , and fixed size =360 then delivery should be split into 3 different ones
Please let me know your thougths
Regards
Shyam
If you get only one PR, then its for the reason that the whole demand is needed on the same day. How would a split into 3 PR help you further if all is needed for exact the same date?
If you plan with weeks, then SAP assumes that anything is due on the last day of the week.
You may need to switch to a different lot size that is not on a weekly basis.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Caetano
Thanks a lot
yes, i checked this and seems it might meet the requirements. In lot sizing procedure i see also the overlapping field. But i am not sure what is meant by the cycle time ..is it the Takt time which we mention in material master?. Please guide.
Also if you have any document with more details on this, that would be helpful
Regards
Shyam
Dear Caetano
Thanks again. Its working as you mentioned. Only one concern is that some delivery dates will fall in Saturday or Sunday . So want to avoid this. All delivery dates should fall on working days.Can we use this Takt time along with a Planning Calendar ?
In Planning Calendar can i define a calendar with all working days and use that along with Takt time . In lot size i will mention Lot-size indicator=K
Will this work? . I tried but seems there is some problem still
Please let me know your views
Shyam
Hello,
Check if Maximum Lot Size in MRP1 view of the material master fulfills your requirements.
Best regards,
Yancho
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi i think Quota Arrangement through it is possible. scn.sap.com/docs/DOC-51785. plz check once Regards Kumar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
109 | |
8 | |
8 | |
6 | |
5 | |
5 | |
5 | |
5 | |
5 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.