Hi Team,
I have an issue with KP98 transaction when copying the actual data to plan data . The problem which I am facing is we are copying period 1 to 6 actuals data to 1 to 6 Forecast version 82 and after executing it copies the data in to old tables COSP but it is not updating FAGLFLEXT table.
We have created a planner profile with summary table FAGLFLEXT and posted the data using KP06 and GP12N.
To update data we are executing FAGL_CO_PLAN transaction and it load the data in to FGALFLEXT table . Please help me to understand why data is not loaded when using KP98 and why it is loading when using FAGL_CO_PLAN.
Thank you
Srivani
Hello Srivani,
Please refer to SAP note 1017289, 1009299, 999614 and 12452.
Thank you,
Ronghua Fan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Srivani
As far as I know, KP98 is meant to copy the Plan / Actual data from one version to another. It is not designed to update FAGL tables
I am not sure if there is an option to copy the data similar way in New GL planning or not. But what you are doing currently seems to be the right way to me
Br, Ajay M
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
98 | |
8 | |
6 | |
6 | |
5 | |
5 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.