Hi all, my question is related to the PR creation under the asset category:

  1. Created PR Against in asset category & GL code and the relevant WBS number is assigned.
  2. Now I’m checking the commitment in PR (after final approval), no commitment is showing against the PR, as well as no commitment is showing in slr558 report.

My requirement is to show this PR cost in commitment cost against the WBS as per the client need.

Please help me which setting I need to cheque in the FI and MM to achieve this.

View Entire Topic
jagdeepsingh83
Active Contributor
0 Kudos

Apart from the basic WBS checks mentioned above. Are you using any custom UOM or any UoM in the PR that is only value-based e.g. Service PRs if yes -- please check the configuration for UoM (T-Code CUNI) and make sure the value-based commitment indicator is checked for specific UoM.

Also check SAP KBA-3221344 - Commitment update not successful for purchase requisition - SAP for Me for your issue.