Hi all, my question is related to the PR creation under the asset category:
My requirement is to show this PR cost in commitment cost against the WBS as per the client need.
Please help me which setting I need to cheque in the FI and MM to achieve this.
Request clarification before answering.
Apart from the basic WBS checks mentioned above. Are you using any custom UOM or any UoM in the PR that is only value-based e.g. Service PRs if yes -- please check the configuration for UoM (T-Code CUNI) and make sure the value-based commitment indicator is checked for specific UoM.
Also check SAP KBA-3221344 - Commitment update not successful for purchase requisition - SAP for Me for your issue.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
What is your Account Assignment on the PR, A for Asset or P(or Q) for Project WBS?
With Account Assignment Asset when the GR posts the value will post directly to the Asset on the Balance Sheet.
To work with budget availability on a WBS and the A account assignment the WBS will have to be statistical. you can't account assign a PR to 2 "real" cost objects.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
| User | Count |
|---|---|
| 33 | |
| 17 | |
| 14 | |
| 13 | |
| 9 | |
| 4 | |
| 2 | |
| 1 | |
| 1 | |
| 1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.