on ‎2011 Oct 13 8:32 AM
Issue in PS Cash Management:
Coming from my sales order (SD billing plan), I get cash management lines item in PS ==> table COFP (Document Lines (project cash management)) with value type 62 (Planned Payments).
Then I invoice the WBS element with VF01. During invoicing, the system creates new line items in COFP with value type 54 (Invoices).
Issue
The problem is that planned payment (value type 62) is not reduced and whatever the invoice is, planned payment are the same.
From my understanding, new lines item should have been created with negative sign in order to reduce planned payment amount. Like invoices are reduce when payment is done.
Who can you confirm?
What are your feeling?
Thanks in advance
Request clarification before answering.
please explain what are the settings you have done for Project Cash Management.
It is not possible to comment based on COFP entries.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
| User | Count |
|---|---|
| 36 | |
| 27 | |
| 21 | |
| 4 | |
| 4 | |
| 4 | |
| 4 | |
| 3 | |
| 3 | |
| 2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.