Hi All,

We are planning to have the RA deriving the POC% from the Progress analysis and which we will maintain in Level 1 WBS. In the back end we have done the settings and also as detailed in the blog Results Analysis Method 7, POC Method Based On Pr... - SAP Community

The following settings are done:

Valuation Method for RA Key with the status is configured in OKG3 with progress version 100 and other settings as below:

misrasuman1_0-1710332278467.png

VC maintenance as below

misrasuman1_1-1710332359027.png

misrasuman1_2-1710332386174.png

Assignment of CE to VC

misrasuman1_3-1710332438193.png

Question : These cost elements are not existing and was copied from client 000. I hope we should assign an existing one.

SKF 30 defined for POC with usage 3

misrasuman1_4-1710332516519.png

SKF is assigned to the VC.

misrasuman1_5-1710332645203.png

However when I run KKA2 I am not getting the POC% which is maintained in the Progress Tab. I am new with this set up but is the POC% taken from the project builder as a part of the standard or is it taken from Progress Analysis after we run CNE1.

Regards,

Suman Misra

 