Is there any resource overview for availability/allocation across SAP modules

yavan1
Newcomer
0 Likes
337

We have created a resource with a personal number in PA30 transaction. We allocated the newly created resource to SAP PS projects, SAP PPM projects, SAP PM order for a particular number of hours. How to find a consolidated overview for the resource allocation, availability and booked time across the modules

Accepted Solutions (1)

Accepted Solutions (1)

Ken_Melching
Product and Topic Expert
Product and Topic Expert
0 Likes

Try Workforce Planning, CMP2 and CMP3, that might show PS and PM as long as they are on the same workcenter.  Unfortunately PPM assignments won't be shown there. 