Is there a way to exclude certain week or month values set in PIR from the MRP calculation range?

SI_y_Ito
Explorer
0 Kudos
362

PIR_example.png

Is there any way to exclude “M03.2025” from the scope of calculation?

 

manage_material_coverage.png

The result I would like is for Available to be -30 PC

03/03/2025 do not want it to be considered

Is there a way to achieve this?

Accepted Solutions (1)

Accepted Solutions (1)

Prabha_A
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hi @SI_y_Ito 

As I can see it is an Independent Requirement, You can change it manually in the Fiori App 'Maintain PIRs' using Mass Edit option.

1) Navigate to Maintain PIRs Fiori App

2) Select the material line item for which you want to change the quantity for spectific period(in your case M03.2025) > click on Edit option

3) Click on Mass Maintenance Option at the top right corner > In the popup, select the Planning period that you want to skip (It can only be current or future period) and Input Proposed quantity as '0' > Click on OK and then Save.

Prabha_A_0-1747313112890.png

In this way, you can change the Independent Requirement Quantity to zero (0) for specific period for multiple materials at a time.

Hope this helps and kindly mark the solution as accepted it if resolves your query.

Thanks,

Prabha A