on 2025 May 20 11:14 AM
Hi,
Is possible to increase the scheduling horizon beyond the 3 numeric numbers (eg 999 maximum) either for Plant or MRP group or both? (Tables T399D or T438M field UMTHZ, data element UMTHZ.)
Many thanks
Adrian
Request clarification before answering.
Hello @AdrianW
Theoretically it is possible to modify the UMTHZ data element and enhance it. However that would lead to a massive regeneration of all dependent objects and quite possibly break the system.
Why do you need to enhance rescheduling period? Are 3 digits not enough? That is almost 3 years!
Best regards
Dominik Tylczynski
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Many thanks for your reply.
We are in the manufactoring industry and have some production items that can take up to 5 years to produce! (Beyond the limit of 999 days)
Fully appreciate that enhancing the data element could have a greater impact on the system than we would wish for.
Are there any BADIs that could adjust the scheduling horizon dynamically?
Thanks Adrian