Is mass change iw38 iw37 at operation level on would possible by mass change?

sap_ankit
Explorer
0 Kudos
1,132

Pl can you clarify mass change of work center iwerks not location or main work center at header. Is there a functionality with std sap or do we require to go for z or enhance std report some how ?

Accepted Solutions (0)

Answers (1)

Answers (1)

NTeunckens
Active Contributor
0 Kudos

Trx. "IW38" (OrderHeader) and "IW37" (OrderOperation) does provide some Mass-Change possibilities.

Check SAP-Help and Notes on "LOG_EAM_CI_5" (EHP6), see the Screenshot of this Presentation (PDF) on "Mass Change Functionality in Plant Maintenance" which enables change of WorkCenter at Operation level ...

Seeing SAP-Note 1552769, it provides Mass-Change-Functions including WorkCenter.

Check out the SAP-Notes on both "IW38" and "IW37" with the Business Function "LOG_EAM_CI_5" or higher.


Hope this helps

Nic T.