on 2025 Mar 19 9:17 PM
We would like to know if it is possible to use a cross plant scenario in production for materials in SAP S/4HANA Public Cloud.
Request clarification before answering.
Hi SAP Community,
Yes, in SAP S/4HANA Public Cloud it is possible to use cross-plant production. In this scenario, a plant withdraws material from another plant or the production plant differs from the planning plant.
Please note that currently the system only supports cross-plant production in the same company code. For more information, kindly check below SAP Help Portal documentation:
Cross-Plant Production
Best Regards,
SAP Support
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
85 | |
12 | |
9 | |
5 | |
4 | |
4 | |
3 | |
2 | |
2 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.