on ‎2025 Mar 19 9:17 PM
We would like to know if it is possible to use a cross plant scenario in production for materials in SAP S/4HANA Public Cloud.
Request clarification before answering.
Hi SAP Community,
Yes, in SAP S/4HANA Public Cloud it is possible to use cross-plant production. In this scenario, a plant withdraws material from another plant or the production plant differs from the planning plant.
Please note that currently the system only supports cross-plant production in the same company code. For more information, kindly check below SAP Help Portal documentation:
Cross-Plant Production
Best Regards,
SAP Support