on 2024 Jul 03 12:17 PM
Hi
SAP S4HANA Public cloud.
I am working with process order and QM at the end (after GR).
QC checks thet there is a must to create rework order to fix a batch.
IS it possible to create rework order in process manufacturing? I have seen rework for production order.
What should be set for such a production?
Regards
MAciej
Hi,
Yes, we can use CORO to create process order with reference to existing process order.
Thanks,
Pruthvee