Is it possible to calculate the new FMEA key figure Action Priority (AP) in SAP?

stefkeil
Explorer
0 Kudos
257

Good Day,

Is it possible to calculate the new FMEA key figure Action Priority (AP) in SAP?

Many greetings

Accepted Solutions (0)

Answers (2)

Answers (2)

stefkeil
Explorer
0 Kudos

The harmonisation of AIAG and VDA results in changes to the FMEA.

These are in brief:

Seven FMEA steps (instead of five in the VDA)

Omission of the RPZ, instead Action Priority (AP) (risk matrix)

Standardised FMEA form New evaluation catalogues

My question is whether it is possible to implement the changes in SAP especially the new AP key figure.

holger_hartung
Contributor
0 Kudos

Hello Steffen,

what do you mean with "new". Something from VDA?

It is possible via oss note to use grafic RPZ