IP02 and IP10 changes effects.

MarGli
Newcomer
0 Likes
347

Hello, 

My division has created second maintanance planner group, and now roughly 200 plans have to be redirected through IP02 to abovementioned group, so that newly generated PM orders would appear in IW38 for new maintanance planner.

Do I simply have to change planner group in IP02, and this would affect already scheduled (but not generated) orders? Or, after making plan changes in IP02, should I also reschedule them in IP10?

Regards,

Martin

Accepted Solutions (0)

Answers (1)

Answers (1)

RAHEEL_BABAR
Active Contributor
0 Likes

Hi,

Yes you need to reschedule maintenance plan via IP10.