res all,

for finished material i am creating inspect lots after GR .for that i have assigned 04 insp.type. now my client requirement is he want inspect first piece and last peice of production .

for that how to create insp.lots .

can system will generate lots or we have to create manual lots.

if manual which type of insp.type we have to assign

thx&regds

prasad

Accepted Solutions (0)

Answers (4)

Answers (4)

Former Member
0 Kudos

thank u

prasad

Former Member
0 Kudos

Hi ,

U can use inspecton type 04 itself ; only in addition u have to use inspection point in the Quality plan.

Regards

Amol

Former Member
0 Kudos

hi amol,

thank u for reply.

and now my query is if we r creating manual lots with 04 type can we differentiate manual lots and system generated lots.please clarify this.

and one more query is we r giving goods to subcontractor for some process.while receving w.r.t to p.o i want to inspect that goods.for that which insp.type i have to assign.

i mean 01 or 0130.what is the diff.b/w

prasad

Former Member
0 Kudos

Hi,

Normally Inspection lot number series will be different for manually created lot and system generated lot.

Ref the link below reg the insp type for subcontracting scenario

Regards

K.M.Arun

Former Member
0 Kudos

Hi,

As arun told you that there is different no range for both manually created lots and automatically created lots.

Secondly you have to assign inspection type 0130 for the material which you are going to receive back after processing.

Amol

Former Member
0 Kudos

hi,

my requirement is whenever i want to create manual insp.lots

and it should be link with particular production order.for that any solution plz explian step by step.

it is very urgent for me .

thanks in advance

prasad

Former Member
0 Kudos

Hi,

Go to QA01 for creating insp lot manually.

In case of 03 or 04 lot origin , dont give material no , give plant and insp lot origin and enter.

After that , it will ask the production order and you can proceed further.

Regards

K.M.Arun

Former Member
0 Kudos

hi arun,

for manual lots i am using 89 insp.type .now my client requirement is he wants to create one inspection lot for first peice and he wants to extend the lot for (means one more partial lot)last peice.b'coz he wants to compare both lots. for that i have created one sampling procedure with indep.multimple samples indicator .

but now my problem is in results recording he wants to create another part.lot for every insp.char individually.so can't we create totally one more lot to compare results.

I hope u understand my query..

thanks in advance

prasad

former_member42744
Active Contributor
0 Kudos

1) Why are you using manual lots?

2) Why not 04 lots with physical samples.

3) Why in the world would the client want a new lot for each characteristic? I would love to hear this business process so I can understand it for future clients some day.

If that is what they want, you need to create one operation for each characteristic. So I would create a plan with

op. 10 - initial sample

op. 20 - test 1

op. 30 - test 2

etc.

etc.

op. 9000 - Final sample.

You sould set up the sample procedures and sample drawing procedure so each operation will have their own physical sample number assigned.

Craig

Former Member
0 Kudos

Hi,

Manually created inspection lots cannot manage stock i.e they are not stock relevant.

You may define your sampling qty appropriately in the inspection plan and use 04 insp type for creating lot automatically.

Regards

K.M.Arun

Former Member
0 Kudos

Hi Prasad...,

If you want to do inspection only twice a day that to for first and last peace of production then create manula inspection lot with inspection type "09". and do the results recording for it.

it will be used for stastical purpose also.

regards.

Former Member
0 Kudos

hi,

thank u for immediate response .

we have to assingn 09 or 89 why b'coz 09 is for recurring insp.

so clarify my doubt