Include PO confirmation reference field in MIGO receipt screen

darrell_hart
Participant
0 Likes
674

The MIGO PO receipt screen includes the fields from the PO confirmations tab such as qty and delivery date per receipt line. I need it to also include the Reference field (Reference Document Number) from the PO confirmations tab.

I have asked our consultants to make this change, but they are instead giving me a very long winded process of creating an in-bound delivery and receipting that. As this will add considerable overhead to our ordering process I am reluctant to do it and want them to address the original request.

So, does anyone here know if my request is actually technically possible. If so, can you please detail how to do it so I can pass this to our consultants.

Thank you

Darrell.

Accepted Solutions (1)

Accepted Solutions (1)

darrell_hart
Participant
0 Likes

This is finally done.  Instead of adding a new field to MIGO, the consultants have made a change which copies the data from this Reference field to display in the Text field of MIGO.   Turns out it was relatively simple.

Answers (1)

Answers (1)

darrell_hart
Participant
0 Likes

Anyone...?

It appears I need to get field EKES-XBLNR into structure GOITEM, so any idea how to do that would be helpful.