Hi All,

in WM what is the inbuond process

1) PO > Inbound using PO > Create TO > Confirm TO > PGR

2) PO > Inbound using PO > PGR> Create TO > Confirm TO

Both are working on different systems but how ?

Accepted Solutions (0)

Answers (1)

Answers (1)

DominikTylczyn
Active Contributor
0 Kudos

Hello 1pa_1

Both are standard LE-WM inbound processes.

To use the 1st process, you need to activate picking relevancy in the delivery item type configuration:

That makes it possible to create transfer orders for inbound delivery placement. Yes, it's a bit confusing - you need to set up "relevant for picking" so you can create placement TOs.

The 1st process is not suitable if you want to create QM inspection lots and place the stock before the usage decision is taken.

Best regards

Dominik Tylczynski

1pa_1
Explorer

Thanks for your clarification.