Hi
One of Work center capacity utilization maintained 85%, while scheduling not able to achieve 100% scheduling of work center and giving "9XXXXXXXXX/0010: Operation cannot be scheduled automatically"
How to achieve 100% scheduling ? due operations how to schedule in same.
Another work center even maintained utilization as 85% 110% scheduling achieved,
Scheduling date are same in both case and capacity Hrs and operating time are same.
Please suggest
Note: We are using S/4 HANA 2021 ,
Request clarification before answering.