when a new service is added in services tab automatically the work hours is calculated(Here 1440 hrs).The requirement is nullify the work hours(0 hrs).How to achieve that ? Is there any user exit for that?

PS: I'm new to SAP.

Accepted Solutions (0)

Answers (2)

Answers (2)

akharisma
Explorer
0 Kudos

Hi...

The work calculated into 1440 hours because you entry 2 Month in the bottom tab Services.

2 Month = 60 days x 24 hours = 1440 hours.

Regards,

Kharisma

MTerence
Active Contributor
0 Kudos

Hi,

The work gets calculated based on the Service Unit you have entered.

If it is Hour / Day / Month, system calculates the work for PM03 control key.

You can maintain service packages with other units like EA.

Regards