on 2024 Feb 13 1:10 AM
After add scope items in CBC systems, the related scope items are not activated in T system.
Request clarification before answering.
Hi,
After adding scope items in CBC implementation project, when you complete "Scope and Organizational Structure Phase Is Completed" task, the scope items will activate in your D system.
Then you need use Export Customizing Transports app in D system and Import Collection app in T system to transport the scope items activated in the development system to a test system.
KBA 3372623 - How to activate scope items in the test system in a 3-System Landscape
Best Regards,
Stephen