on ‎2010 Mar 02 6:10 AM
Hi Experts,
I have some PO's which is matrial we have received short, Now we want to short close these PO, Please guide me how i can short close the pending purchase orders.
Regards,
ViAngrish.
Request clarification before answering.
Hi
You need to tick delivery completed indicator in Delivery tab or Make PO qty = Delivered qty.
Regards
Antony
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Solved! thanx everybody
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
HI,
Go to ME2n and give we101 and click on dynamic selection
go to Purchase Document Header .....here delivery complete indicator ...put X there and excecute.
Hope Help U !
Regards,
pardeep Malik
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
See transaction code
ME2M : based on Material
ME2L : Based on Vendor
ME2N : Based on Purchase Order No.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
How to short close bulk purchase orders which are in hold, using ABAP program. Please advise.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
| User | Count |
|---|---|
| 39 | |
| 26 | |
| 21 | |
| 5 | |
| 4 | |
| 4 | |
| 4 | |
| 3 | |
| 2 | |
| 2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.