How to set tolerence limit for planned service entry sheet net value with respect to PO value

Former Member
0 Kudos
1,995

Hi,

In Planned Service sceanrio, Standard system able to check the quantity tolerance only, not checking tolerence limit for Planned Service value.

Our requirement is to update "Gross Price" manually in Planned Service entry sheet. we get this option by creating Service PO with “Price
Change Allowed“
check box in “Service” tab at item level.

But issue is no option to control tolerance limit of Service entry sheets value (ie, System allow to create service entry
sheet for a PO to any value)

please advice us how to control this.

View Entire Topic
Former Member
0 Kudos

Hi,

that service po is legal document,at the time you raise the po u know the values and qty.

tol.limit u can give the po it self (in service item)

that SES price we can not change, that is slandered process

1.go through the unplanned service or(not match the po value)

2. change the PO Prices 

as of my knowledge

Regards