How to set 'Task successful' status mandatory for particular tasks in a QM notification?

dhineshpanneer
Explorer
0 Kudos
1,743

I have 5 tasks in my Deviation notification. I want one particular task to be made TSCO TSSC (Task completed and then made successful) status, else it should not allow the user to complete the notification. How do I achieve this?

View Entire Topic
Prasath
Contributor

Hi Dhinesh,

Hope that Status profile will solve your problem. Kindly look into the following and try it. You can customize your own profile as per the requirement.

Regards,

Prasath E