how to set mandatory BOM explosion before saving a transaction ?

maheshkumar_komatineni
Active Participant
0 Kudos

Hi ,

an any Body please let me know how to set a control for mandatory  BOM explosion  before saving a transaction in MIGO.

Regards,

Mahesh.

Accepted Solutions (0)

Answers (1)

Answers (1)

RahulHanda
Active Contributor
0 Kudos

Hi Mahesh,

Could you provide more details what exactly you are doing in MIGO. Are you working with sub-contracting PO where you want to explode BOM or production order where you want to do GI or some other scenario?

Regards

Rahul

maheshkumar_komatineni
Active Participant
0 Kudos

Hi rahul,

thank you for the response . my issue is we are doing sub contracting process . while doing vendor returns of sub contract FG materials . some time users are not exploding the BOM when they change Header quantities. so system is posting wrong quantities. so we want use a control  like mandatory BOM explosion while doing the 122 movement.

Regards,

Mahesh

RahulHanda
Active Contributor
0 Kudos

Hi Mahesh,

You can check with ABAPer for enhancement point in MIGO for GOITEM-EXPAND. In your case you have to expand and exlpode the BOM as we have in ME21n/22n. Use function MEPO1319BOMEXP for the same.

Go through the below link to get an overview and work with ABAPer for the same. Also check in ME21n on material data tab how it's exploded again for you reference.

Let me know if it worked for yourself.

Regards

Rahul

0 Kudos

Hi Mahesh,

Why do you want to send/reverse the components when they were actually assembled.

Logically there is a defect found in an assembly assembled by subcontracter. So we would send back only the assembly back for rework. We can create a return PO to handle this right?

BR

Raghava